RAAF Base Amberley – National Airfield Maintenance Works
About the project
The full demolition and reconstruction of the runway pavement works took place in an extremely tight, eight week window prior to the Christmas period, with the airfield operating with constant aircraft movements throughout construction and the relocation of key aircraft to Darwin to enable construction.
Prior to the opening of the main runway, BMD conducted a full flight test of the new high intensity approach lights installation and the new section of runway and liaised closely with the Department of Defence to bring back aircraft and maintenance crew two days early for Christmas.
Outcomes
Prior to the closure of the runway, BMD installed a temporary position approach path indicator on the main runway and temporary aircraft arrestors for the F18’s on the main and cross runways. Over a single weekend, BMD installed the displaced threshold equipment and all associated temporary line markings to Civil Aviation Security Authority specifications.
One of the key challenges on the project was the importation and placement of highly specified and technically demanding unbound, bound and asphaltic airport pavements and full quality certification within the tight delivery timeframe. In order to achieve the requirements, the project needed to be carefully planned, with major suppliers and subcontractors requiring detailed daily schedules for manufacture, supply and incorporation from three to four months prior to the start of works.
The demolition works of the existing 60 year old concrete pavement were completed over a five day period of day and night shifts. The spoil gravel material from the demolition works was relocated on base to extend a current hard stand area used for training purposes saving money on importing new material.
As a result of the detailed planning, up to 5,000 tonnes per day of pavement was placed and compacted to specification during the day, with full MARCO proof-rolling completed at night to maintain the program.
The airfield specifications took additional engineering to ensure the high aviation sector standards were met or exceeded. Ground conditions onsite were poor, with an extremely plastic subgrade and high water table. The solution included a combined lime/cement stabilisation of the subgrade and several unbound pavement layers of flexible pavement