About the project

Located at Webb Dock in Port Melbourne, 10 minutes outside Melbourne's CBD, the project reconfigured and redeveloped Webb Dock East, returning it to its original role as an international container handling facility.

The upgraded facility is one of the most technologically advanced, environmentally sustainable and safest container terminals in the world, capable of handling the equivalent at least one million shipping containers per annum.

6
20160711_093350
BMD Constructions_Port Capacity Project - Roads and Services_Victoria 3
20170310_rrp8819

Scope

Earthworks

Construction of pavements

Wharf works

Rail works for automatic stacking cranes

Rail works for ship-to-shore cranes

Installation of drainage

Electrical and communication conducting

Environmental works

Water supply and fire services

Demolition

Concrete works

Marine works

Ground improvement

Highlights and outcomes

BMD Constructions completed the project under budget and five months ahead of schedule.

The project team focused heavily on safety throughout the project, implementing preventative education toolbox sessions, varieties of training, interactive prestart workshops, health checks, targeted inspections, positive intervention incentives, and the introduction of plant call numbers attached to earth moving equipment to maintain safety and positive communication onsite. This strong safety culture resulted in the team achieving 1.8 million man hours lost time injury free.BMD contributed to the project's achievement of an Infrastructure Sustainability Council of Australia design rating of 'Leading', which is the highest rating category a project can achieve in the infrastructure sustainability scheme. This outstanding achievement demonstrates what can be accomplished when a project embraces sustainability in their design process.

BMD Constructions completed the project under budget and five months ahead of schedule.

The team achieved 1.8 million hours lost time injury free

The project achieved an Infrastructure Sustainability Council of Australia design rating of 'Leading'

BMD consistently delivered on meeting our expectations as their client and contributed to the completion of the project five months ahead of schedule and under budget. The efficient and safe construction of the VICT project is a credit to BMD and I would be happy to work with the BMD team again.

Anders Dømmestrup, Chief Executive Officer, Victoria International Container Terminal Limited

Awards

ipa-oration-352

Infrastructure Partnerships Australia | National Infrastructure Awards | Smart Infrastructure Project Award

AA3I2416.jpg

Engineers Australia | Australian Engineering Excellence Awards | Infrastructure Category